This project was a new build project that included the following scope of works:
- Clearance of entire site with all excess material taken off site.
- Relocation of trees on site
- Installation of post and rail fencing with mesh wire
- Laying of surface water piping throughout site
- Removal of stone wall along roadway.
- Excavation and forming of a split level area
Walking track to include:
- Excavation for proposed two meter wide walking track
- Installation of new drainage system
- Install manholes
- Lay terram geotextile under walkway
- Lay ci804 stone and a lime dust finish on walkway